Skip to main content

The Armenian American Museum is a two-phase project including the Phase I Foundation Phase featuring the one-level semi-subterranean parking garage and foundation of the building followed by the Phase II Horizon Phase featuring the two-level 50,820 square foot museum complex. The Phase I construction began in Summer 2021 and will be completed in Summer 2022. The Phase II construction is anticipated to begin in Summer 2022 and complete in Summer 2024.

Summer 2021

Groundbreaking

The historic Groundbreaking Ceremony was celebrated with thousands of friends and supporters in July 2021.

Phase I Construction

The Phase I Foundation Phase features the one-level semi-subterranean parking garage and building foundation.

Summer 2022

Phase II Construction

The Phase II Horizon Phase features the two-level 50,820 square foot museum complex.

Summer 2024

Grand Opening

The Grand Opening will officially celebrate the opening of the museum to the general public.